Hot-Dip Galvanized OHE Outriggers – WDFCC CTP-11 Railway Project
Project Description
Fabrication and manual erection of hot-dip galvanized outriggers for Over-Head Equipment (OHE) foundations along the Western Dedicated Freight Corridor (WDFCC) viaduct sections at Kalamboli and Kopar, Maharashtra. Work was executed as a balance works contract under Tata Projects Limited, the prime contractor for DFCCIL. All work was carried out strictly as per approved drawings and site engineer instructions.

Materials Used
Hot-dip galvanized steel (outrigger assemblies)
Technical Specifications
- Complete supply, fabrication, and erection scope including all manpower and resources
- Hot-dip galvanizing finish for corrosion protection
- Executed across active railway viaduct sites at Kalamboli and Kopar
Scale / Quantity
50 Metric Tons total (split across two work phases of 19.5 MT and 30.5 MT)